Paper 1 · Investment Appraisal

The net present values of a project have been calculated as follows: | | NPV ($) | | --- | ---: | | at 10% | 40 000 | | at 20% | (18 000) | What is the internal rate of return on the project?

A10.69%
B13.10%
C16.90%
D20%

ZIMSEC Accounting 6001/1 Paper 1 (Multiple Choice), November 2022, Q36